About the Project
In an ongoing effort to provide quality wireless service, Verizon Wireless has identified your community as one that will benefit from improved network coverage.
Milestone Towers is proposing a wireless telecommunications facility at the Claiborne Interchange or the junction of Interstate 95 and Route 1.
The proposal is for a 165-foot monopole and will include ground equipment required to operate the facility.
This equipment will be located at the base of the structure in a secure fenced area. Verizon Wireless will be the first wireless carrier to locate on the proposed tower.
Update #1: Online Town Hall: On Thursday, November 30th @ 6:00 pm we will hold an online Town Hall webinar consisting of a short presentation followed by a question and answer time. Registration is required and can be completed on the Town Hall page.
Our Process
1. Due Diligence
Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.
2. Land Use
Conditional Use Permit Application, Community Meeting, Staff Review, Planning Commission, Board of Supervisors.
3. Permitting
Conduct Bid Walk With Contractors, submit Site Plan and Building permit applications.
4. Construction
Tower construction = 4-6 weeks | Carrier construction = 4-6 weeks on average
On-site supervision by Construction Manager.
5. Site Maintenance
Four visits per year for site maintenance | Remove trash, debris, check signage.
2-4 visits per year for carrier modifications.